18 communities · 2,995 MW proposed IT · 4.6 kW per resident · Year-round food · River protection · Waste heat reuse · Free charging · Subsidised renewable fuels · Transparent permitting status
COLUMBIA RIVER · WASHINGTON

Show the assumptions. Show the constraints.

A credible community infrastructure proposal distinguishes a mapped idea from permissions, finance, water rights or delivered public benefits.

18 planned nodes2,995 MW ITNot yet authorised

What has been established — and what has not

✓

Population and arithmetic

2020 incorporated place counts; 18 nodes; 4.6 kW per resident; 2,994.9956 MW total.

✓

River geography

Approximate town-centre coordinates and schematic tributary connections; no parcels selected.

✓

Photos

Original real place photos linked from Wikimedia Commons with source pages and usage rights.

No representation of obtained permits or supply

Land parcelsNot selected
Grid interconnectionNot secured
Environmental permitsNot submitted
Community benefit financeNot committed
River permitsNot secured
Fibre systemConcept only

Special regulatory alerts · as of 21 November 2026

Pasco adopted a temporary six-month moratorium on 20 July 2026. Unincorporated Yakima County imposed a six-month data-centre moratorium in August 2026 and subsequently considered its scope. Individual city and county ordinances can change; verify again before filing.