COLUMBIA RIVER · WASHINGTON

Ask difficult questions. Demand specific answers.

Water, electricity, permits, noise, carbon accounting and guaranteed community benefits all deserve publicly auditable answers.

18 planned nodes2,995 MW ITNot yet authorised

Questions worth asking before any construction

Is this project already approved?

No. The network is a conceptual study and none of its proposed node capacities are permitted, financed or connected.

Is it exactly 3 GW?

The selected 18 incorporated towns total 651,086 residents in the 2020 Census. At 4.6 kW each they total 2,994.9956 MW of IT, or about 2.995 GW.

Does river cooling consume no water?

No such claim is made. Any river withdrawal and thermal discharge need measurement, legal approval and ecological assessment.

Why is Pasco included during a moratorium?

The population rule includes the city as a potential community beneficiary; that does not make new data-centre permits available. Its allocation is conditional, not an application.

Why use 2020 Census rather than 2026 estimates?

Using a single auditable census year avoids mixing municipal estimates. The capacity schedule can be re-run with an official consistent later year.

Are the town photographs AI-generated?

No. The photographs link to the original Wikimedia Commons file pages. The engineering diagrams are clearly labelled conceptual graphics.

How would data centres interconnect?

Fibre ring topology and resilient network equipment are proposed, not specified or bought. Latency, rights-of-way and redundancy need engineering studies.

Would food and vehicles really be free?

That is the objective, not a current guarantee. Unit economics, programme eligibility and legally binding financing must be proven.

Is a site plan a zoning application?

No. Town reference coordinates and sample layouts are not parcels or submitted applications.